3.COVERAGE
      1. Coverage (Covered area)
      2. Coverage (Covered area) will be used for certain farm work ability of certain period, which is a seasonal period of for a crop.

        Coverage is simply obtained by following process.

        CA = DC * AWD  / N            Eq. 3-1

        CAS = DC * AWD / M / N                 Eq. 3-2

        CAS = EFC * ANWH / N            Eq. 3-3

        CAW = CA

        where,

        symbol

        term

        unit

        CA

        Coverage (Covered area)

        ha

        CAS

        Coverage of one set

        ha

        DC

        Daily capacity

        ha/d

        AWD

        Available work days

        d

        EFC

        Effective field capacity

        ha/h

        ANWH

        Available net working hour

        h

        M *

        Number of machine set

        -

        N *

        Number of operation times

        -

        * : normally M and N = 1

         

        Example: Next table and See fm-311.xls and fm-33.xls.

        Table 311. Example of Covered Area

        Item

        Effective Field

        Capacity

        Daily

        Capacity

        Available

        work days

        No.

        operation

        Covered

        area

        Work

        Name

        Implement

        Work

        hour

        Net

        Work

        rate

        Net

        Work

        Daily

        Capacity

        Operation Period

        Days of work period

        Rate of

        available work day

        Available

        work days

        symbol

        EFC

        Dt

        NWR

        Dn

        DC

        WP

        DWP

        ADR

        AWD

        N

        CAS

        unit

        ha/h

        h/d

        %

        h/d

        ha/d

        date

        d

        %

        d

        -

        ha

        Tillage

        Rotary 1.8m

        0.266

        10.0

        72

        7.2

        1.92

        Apr.1-May 20

        50

        74

        37.0

        1

        71.0

        Harrowing

        Paddy harrow

        1.132

        10.5

        70

        7.4

        8.32

        May.1-May 20

        20

        73

        14.6

        2

        60.7

        Trans-planting

        Rice transplanter

        2-row

        0.036

        10.5

        67

        7.0

        0.26

        May.1-May 20

        20

        73

        14.6

        1

        3.7

        Herbicide

        Knapsack power sprayer

        1.800

        11.0

        80

        8.8

        15.84

        July 1-July 5

        5

        60

        3.0

        1

        47.5

        Harvest

        Head-feeding combine

        0.052

        8.5

        65

        5.5

        0.29

        Sep.25-Nov.10

        47

        65

        30.6

        1

        8.8

         

        Exercise. 3-1, 3-2

         

        Fig. 3 Flow chart to obtain coverage

         

        3-2. Available Work Days

        Available work days means actual days available to work.

        Freezing temperatures, precipitation, excessive deficient soil moistures, and other weather related factors may limit field machines operations. As weather variability is great, any prediction of the number of future working days can only be made probabilistically.

        The number of working days in any time period is a function of: climatic region, slope of soil surface, soil type, drainage characteristics, operation to be performed, and traction devices.

         

        AWD = DWP * ADR                 Eq. 3-4

        Where,

        symbol

        term

        unit

        AWD

        Available work days

        d

        DWP

        Days of work period

        d

        ADR

        Rate of available work days

        %

        Table 32. Example of Available work days

        Work

        Name

        Implement

        Effective Field Capacity

        Net

        Work

        hours

        Daily

        Capacity

        Working

        period

        Days of work period

        Rate of

        avail-

        able work

        day

        Avail-able

        work days

        EFC

        Dn

        DC

        WP

        DWP

        ADR

        AWD

        ha/h

        h/d

        ha/d

        date

        to date

        d

        %

        d

        Tillage

        Bottom plow 14"x2

        0.224

        7.2

        1.61

        Apr.1-

        May 20

        50

        74

        37.0

        Tillage

        Rotary 1.8m

        0.266

        7.2

        1.92

        Apr.1-

        May 20

        50

        74

        37.0

        Harrowing

        Paddy harrow 20

        1.132

        7.4

        8.32

        May.1-

        May 20

        20

        73

        14.6

        Trans-planting

        Rice trans-planter

        2-row

        0.036

        7.0

        0.26

        May.1-

        May 20

        20

        73

        14.6

        Exercise. 3-3

         

        1. Available net working hour

        ANWH = AWD * Dn                       Eq. 3-5

        Where,

        symbol

        term

        unit

        ANWH

        Available net working hour

        h

        AWD

        Available work days

        d

        Dn

        Net working hours

        h/d

 

        3-3. Rate of Available Work Days

        In the work period, machines are not available for use due to the precipitation and periodical machine maintenance etc. Therefore, these unavailable days are deducted from total work days of the period.

        The weather condition and its suitability to out side work can be get in the weather chart for agriculture which was gathered by meteorological agency.

        Table 33a shows the rate of monthly available work day based on the data of “available work days at outside”.

        Table 33a. The Rate of Monthly Available Days for Machinery Work with Judging from Weather (%)

        Month

        Area Place

        Jan.

        Feb.

        Mar.

        April

        May

        June

        July

        Aug.

        Sept.

        Oct.

        Nov.

        Dec.

        Hokkaido

        Sapporo

        0

        0

        0

        73

        73

        70

        71

        69

        75

        61

        57

        0

        Kanto

        Kumagaya

        90

        88

        84

        75

        73

        62

        71

        82

        67

        74

        87

        94

        Okinawa

        Naha

        77

        75

        77

        68

        60

        52

        74

        65

        73

        74

        82

        77

        rainfall less than 10mm/d

        See fm-33a.xls (for upland work see ASAE-D497)

        Exercise. 3-4

         

        3-4. Coverage of a Farm Work, or a Farm Work System
        1. Coverage of combined work

        See 5-1-6. Coverage of plural farm works

         

        3-5. Machinery capacity
        1. Machinery capacity from Coverage
        2. How to obtain the optimal machinery capacity, when farm scale or coverage of farm system is given?

          DC = CA * N / AWD                 Eq. 3-6

          EFC = DC / Dn                          Eq. 3-7

          TFC = EFC / EF * 100              Eq. 3-8

          Where,

          symbol

          term

          unit

          tillage 1

          tillage 2

          TFC

          Theoretical Field Capacity

          ha/h

          0.315

          0.360

          EF

          Field Efficiency

          %

          71.0

          74.0

          EFC

          Effective Field Capacity

          ha/h

          0.224

          0.266

          Dn

          Net working hours

          h/d

          7.2

          7.2

          DC

          Daily Capacity

          ha/d

          1.61

          1.92

          AWD

          Available work days

          d

          37

          37

          N

          No. of operation

          -

          1

          1

          CA

          Coverage

          ha

          59.6

          71.0

          Example: Obtaining EFC, TFC from Coverage in above case.

          Exercise. 3-5, 3-6

        3. Selection of machine

        From equation 2-9,

        W = (TFC / V) * 10                   Eq. 3-9

        Table 352 Example: Obtaining machine width from TFC

        symbol

        term

        unit

        Example

         

        Work name

         

        Tillage 1

        Tillage 2

         

        Implement

         

        Bottom plow

        Rotary

        TFC

        Theoretical Field Capacity

        ha/h

        0.315

        0.360

        V

        Speed

        km/h

        4.5

        2.0

        W

        Width

        m

        0.7

        1.8

        See fm-351.xls

        Exercise. 3-7

         

        3-6. Exercise

 

Exercise 3-1.

When Daily capacity =0.48 ha/d, Available work days =21 d, obtain Coverage of one set.

Exercise 3-2.

When Effective field capacity =0.009 ha/h, Number of workers = 5, Available work days =21.9 d, Net work hour=6.4h/d , obtain Coverage of this manual weeding.

Exercise 3-3.

When Days of farm work period =(April 10 to 24), Rate of available work days = 75%, obtain Available work days.

Exercise 3-4.

Pick up a farm work in your country (Example: tillage). Select a machine and list up width and speed.

1. Obtain Theoretical Field capacity (TFC) and Effective Field capacity (EFC).

2. Obtain Daily capacity (DC) by using working hour per day (Dt) and Daily net working rate (NWR).

3. Obtain coverage (CA) of the farm work using operation period (DWP) and rate of available work days (AWDR).

4. Submit paper and FD.

Exercise 3-5.

When Coverage (CA)=3.7ha, Number of operation times (N) =1, Available work days (AWD) =14.6d, Net working hours (Dn) =7.0 h/d, Field Efficiency (EF) =55.0%, obtain Daily Capacity (DC), Effective Field Capacity (EFC) and Theoretical Field Capacity (TFC) of this farm work.

Exercise 3-6.

When Coverage (CA)=60.7ha, Number of operation times (N) =2, Available work days (AWD) =14.6d, Net working hours (Dn) =7.4 h/d, Field Efficiency (EF) =82.0%, obtain Daily Capacity (DC), Effective Field Capacity (EFC) and Theoretical Field Capacity (TFC) of this farm work.

Exercise 3-7.

When Theoretical Field Capacity (TFC) =0.135 ha/h, Speed(V) =1.8km/h , obtain Width(W) of machine for this farm work.