Daily Capacity will be expressed the value on a farm work by several sets of machine with operators in the several field blocks on a day. In manual farm work, Daily Capacity will be expressed the value by a group of several workers.
Daily Capacity
DC = EFC * Dn Eq. 2-26 Dn = Dt * (NWR / 100) Eq. 2-27
From above two equations,
DC = EFC * Dt * (NWR / 100) Eq. 2-28Where,
symbol |
term |
unit |
DC |
Daily Capacity |
ha/d |
EFC |
Effective Field Capacity |
ha/h |
Dn |
Net Work hours per day |
h/d |
Dt |
Working hours per day |
h/d |
NWR |
Daily net working rate |
% |
Table 241. Daily Capacity of farm work
Work Name |
Machinery |
Effective Field Capacity |
Work capacity |
Work hour per day |
Net Work rate |
Net Work hours |
Daily Capacity |
EFC |
WC |
Dt |
NWR |
Dn |
DC |
||
unit |
ha/h |
h/ha |
h/d |
% |
h/d |
ha/d |
|
Land preparation |
Walking Tractor + Rotary |
0.083 |
12.0 |
8.0 |
75 |
6.0 |
0.50 |
Weeding |
Manual |
0.009 |
111.1 |
8.0 |
80 |
6.4 |
0.06 |
Sowing |
Walking Tractor + 2-Row Seeder |
0.126 |
7.9 |
8.0 |
65 |
5.2 |
0.66 |
Trans-planting |
Rice transplanter |
0.036 |
27.8 |
10.0 |
73 |
7.3 |
0.26 |
Chemical application |
Boom sprayer |
0.273 |
3.7 |
8.0 |
75 |
6.0 |
1.64 |
Harvesting |
Head-feeding combine |
0.052 |
19.2 |
8.0 |
68 |
5.4 |
0.28 |
Exercise. 2-14
Dt = Dn + Dp + Ds + Dc + Df + Da + Dm + Dr + Db Eq.
-1Where,
symbol |
term |
unit |
Dt |
Total daily working hours |
h |
Dn |
Net working hours |
h |
Dp |
Preparation time of work |
h |
Ds |
Time for setting |
h |
Dc |
Time for cleaning of farm machines |
h |
Df |
Time for feeding |
h |
Da |
Adjustment time |
h |
Dm |
Moving or traveling time |
h |
Dr |
Repairing time |
h |
Db |
Short brake time or time for non operation or lunch time |
h |
Table 242. Actual survey of daily work hours
(Harrowing by disk harrow, and plowing)
Items |
Clock Time |
Items of required hours |
Area |
Remarks |
||||||||||||
Starting time |
Ending time |
Net hours |
Net Working hours: Dn |
Other extra hours |
||||||||||||
Plow |
Disk harrow |
Dp |
Db |
Ds |
Dc+ Df |
Da |
Dm |
Dr |
||||||||
h.min |
ha |
ha/h |
||||||||||||||
Garage-Field 1 |
7.02 |
7.19 |
17 |
2 |
10 |
5 |
||||||||||
Field 1 |
7.19 |
9.53 |
2.34 |
2.31 |
3 |
0.445 |
0.178 |
|||||||||
Field 2 |
9.53 |
11.15 |
1.22 |
1.07 |
3 |
10 |
2 |
0.164 |
0.15 |
|||||||
Field 2-Garage |
11.15 |
11.44 |
29 |
4 |
9 |
10 |
6 |
fueling |
||||||||
Lunch Time |
11.44 |
13.31 |
1.47 |
1.47 |
||||||||||||
Garage-Field 3 |
13.31 |
13.39 |
8 |
1 |
4 |
3 |
||||||||||
Field 3 |
13.39 |
17.00 |
3.21 |
3.19 |
2 |
0.5 |
0.151 |
|||||||||
Field 3-Garage |
17.00 |
17.12 |
12 |
7 |
4 |
1 |
||||||||||
Garage-Field 1 |
17.12 |
17.21 |
9 |
5 |
4 |
|||||||||||
Field 1 |
17.21 |
18.34 |
1.15 |
1.14 |
1 |
0.445 |
0.361 |
|||||||||
Field 1-Garage |
18.3 |
18.53 |
17 |
2 |
10 |
5 |
||||||||||
Total (min) |
7.2 |
18.53 |
711 |
417 |
74 |
13 |
126 |
11 |
30 |
31 |
9 |
1.11 |
0.16 |
|||
Rate (%) |
100 |
58.6 |
10.4 |
1.8 |
17.7 |
1.5 |
4.2 |
4.4 |
1.3 |
|||||||
Daily net working rate |
69.0 % |
Where, Dt: Total daily working hours
Dn: Net working hours
Dp: Preparation time of work
Ds: Time for setting
Dc: Time for cleaning of farm machines
Df: Time for feeding
Da: Adjustment time
Dm: Moving or traveling time
Dr: Repairing time
Db: Short brake time or time for non operation or lunch time
Exercise. 2-15
NWR = Dn / Dt * 100 Eq. 2-30
Where,
symbol |
term |
unit |
NWR |
Daily net working rate |
% |
Dn |
Net working hours |
h |
Dt |
Total daily working hours |
h |
Exercise. 2-16
Table 243a. Standard Value of Daily Net Working Rate
Name of operation |
Daily Net Working Rate (%) |
Main equipment |
|||||
One operator |
Two operators |
||||||
Distribution of field |
Distribution of field |
||||||
Small |
Mid. |
Large |
Small |
Mid. |
Large |
||
plowing |
66 |
69 |
72 |
78 |
81 |
84 |
Suki, Bottom plow, Rotary |
Harrowing & leveling |
68 |
71 |
73 |
80 |
83 |
85 |
Disk harrow, Rotary tooth harrow |
Pressing |
70 |
73 |
76 |
81 |
84 |
86 |
Roller, Culti- packer |
Puddling |
63 |
66 |
70 |
75 |
78 |
80 |
Rake, Puddling-rotor. Rotary |
Fertilizer & sowing |
55 |
60 |
65 |
70 |
74 |
77 |
Manure spreader, Lime sower, Broad-caster, Grain drill |
Rice transplanting |
59 |
63 |
67 |
70 |
75 |
80 |
Rice transplanter |
Chemical spray (liquid water) |
62 |
64 |
66 |
69 |
73 |
75 |
Power mist sprayer |
Chemical spray (duster) |
69 |
73 |
75 |
73 |
78 |
82 |
Power duster |
Chemical spray (granule) |
72 |
76 |
80 |
80 |
84 |
88 |
Knapsack type power duster, Manual broad-caster |
Reaping |
62 |
65 |
68 |
72 |
76 |
80 |
Power reaper |
Reaping & binding |
60 |
63 |
66 |
70 |
74 |
78 |
Reaper binder |
Harvesting & threshing |
58 |
62 |
65 |
68 |
72 |
76 |
Head feeding combine. |
Threshing |
70 |
75 |
80 |
75 |
80 |
85 |
Self feeding thresher (Threshing in the field) |
Husking |
85 |
85 |
85 |
85 |
85 |
85 |
Automatic husker (in-door operation) |
Transporting |
75 |
73 |
80 |
80 |
83 |
85 |
Trailer |
Table 243a was estimated by following condition.
(1) If two operator, it can reduce in time for attaching equipment to tractor, cleaning time, adjustment and repair time.
(2) Small, Mid and Large means distribution of field, Large means 100 ha with 5 distribution plots, middle means 50 ha with 3 distribution plots, small means 30 ha with one plots. Traveling speed of tractor in 8 km/hr and others are 5 km/hr.
(3) These net work rates are calculated in Japanese condition.
Table 244b. Working hours per day in Japan
month North latitude (name of place |
January |
February |
March |
April |
May |
June |
July |
August |
September |
October |
November |
December |
26.13 (Naha, Okinawa) |
8.8 |
8.4 |
9.0 |
9.9 |
10.5 |
10.8 |
10.6 |
10.0 |
9.3 |
8.5 |
7.8 |
7.5 |
35.30 (Tokyo, Ibaraki) |
7.1 |
7.9 |
9.0 |
10.1 |
11.0 |
11.5 |
11.3 |
10.6 |
9.4 |
8.4 |
7.5 |
6.9 |
Field map
Table 244e. Farm road conditions
Effective width |
machine width + 1 m |
Standard |
>2.5 m |
Tractor (30PS) |
|
>3.0 m |
Tractor (40-80PS) |
|
>4.0 m |
Tractor (>90PS) |
|
Junction width |
>3 m |
|
Height between paddy field and road |
<30cm |
Tractor |
<20cm |
Combine(0.8-1.2m) |
|
<25cm |
Combine(1.2-3.5m) |
|
<40cm |
Combine(>3.5m) |
Exercise 2-1.
When field area=2 ha, total time required a farm work=5 h, obtain Effective Field Capacity and Work Capacity.
Exercise 2-2.
When field area=20a, total time required a farm work=50min, obtain Effective Field Capacity and Work Capacity.
Exercise 2-3.
When field area=1.2 ha, actual operating time required a farm work=1.5 h, Obtain Effective Field Capacity and Work Capacity.
Exercise 2-4.
When rice grain 800kg was produced in 30min by thresher. Yield of rice was 4t/ha. Obtain Effective Field Capacity of this thresher.
Exercise 2-5.
In plowing of the field (40*30 m), data of times required was as follows.
min: second |
||
ta |
Actual operating time |
13: 36 |
tb |
Turning time |
8: 46 |
tc |
Moving time |
0: 30 |
td |
Regulating time |
1: 06 |
Other time |
0 |
Obtain Total operating time, and Effective field capacity.
Exercise 2-6.
When Wt and Vt were as follows, obtain theoretical field capacity.
Wt |
Theoretical operation width |
0.6 m |
Vt |
Theoretical operation speed |
3 km/h |
Exercise 2-7.
Obtain theoretical operation width of weeding by rotary weeder (width=45cm), when row width is 70 cm.
Exercise 2-8.
Obtain Field Efficiency in percentage, when EFC=1.3, TFC=1.7 (ha/h).
Exercise 2-9.
Obtain Field Efficiency in percentage, in Exercise 2-5.
Exercise 2-10.
Obtain Total time of labor and Effective Field capacity of a set of threshing, when A = 0.2 ha, time required of machie=0.7 h, number of workers=3.
Exercise 2-11.
Obtain Effective Field capacity of manual weeding, when A = 0.2 ha, time required =0.6 h, number of workers=5.
Exercise 2-12.
Obtain Effective Field capacity and Work capacity in case of tillage by power tiller, when W=0.6m, V=1.8km/h, EF=70%.
Exercise 2-13.
Show the effect of size of field (A=0.1, 0.3, 0.5, 1.0 ha),and the effect of shape of field ( m=1, 2, 3.3) in the rotary tillage in upland as follows.
Use next equation. EFC = A / {4.72*A + 0.358* SQRT(A/m) + 0.164}
x |
Width of field |
50 |
m |
y |
Length of field |
100 |
m |
w |
Operating width |
1.6 |
m |
v |
0perating speed |
0.4 |
m/s |
tc |
Moving time in field |
100 |
s |
td |
Regulating time |
530 |
s |
te |
Rest time |
0 |
s |
t1 |
U type turning time |
30 |
s |
t2 |
Δ type turning time |
60 |
s |
Exercise 2-14.
Obtain Daily Capacity and Net Work hours per day, when Dt=8h, NWR =70% and EFC=0.2 ha/h.
Exercise 2-15.
Show working hours per day in your countries.
month North latitude (Name of place) |
Jan. |
Feb. |
Mar. |
April |
May |
June |
July |
Aug. |
Sept. |
Oct. |
Nov. |
Dec. |
Your country |
||||||||||||
35.30 (Tokyo, Ibaraki) |
7.1 |
7.9 |
9.0 |
10.1 |
11.0 |
11.5 |
11.3 |
10.6 |
9.4 |
8.4 |
7.5 |
6.9 |
Exercise 2-16.
Obtain Daily Net Work Rate (NWR) using following data.
Items |
Needed Time |
Items of required hours |
|||||||||
Starting time |
Ending time |
Working hours |
Other extra hours |
||||||||
Plow |
Disk harrow |
Dp |
Db |
Ds |
Dc+Df |
Da |
Dm |
Dr |
|||
h. min |
h. min |
min |
min |
min |
min |
min |
min |
min |
min |
min |
|
Garage-Field 1 |
7.00 |
7.20 |
3 |
10 |
7 |
||||||
Field 1 (0.5ha) |
7.20 |
9.55 |
151 |
4 |
|||||||
Field 2 (0.16ha) |
9.55 |
11.19 |
66 |
5 |
10 |
3 |
|||||
Field 2-Garage |
11.19 |
11.45 |
4 |
9 |
7 |
6 |
|||||
Lunch Time |
11.45 |
13.30 |
105 |
||||||||
Garage-Field 3 |
13.30 |
13.40 |
1 |
6 |
3 |
||||||
Field 3 (0.6ha) |
13.40 |
17.00 |
198 |
2 |
|||||||
Field 3-Garage |
17.00 |
17.15 |
10 |
4 |
1 |
||||||
Garage-Field 1 |
17.15 |
17.20 |
4 |
1 |
|||||||
Field 1: Disk harrow |
17.20 |
18.40 |
77 |
3 |
|||||||
Field 1-Garage |
18.40 |
18.55 |
2 |
8 |
5 |
return to menu to 3. COVERAGE to top
2004/5/30